Breeze Meguro update

By joe on Sun 10/04/09   0 Comments

The Breeze is looking more and more like a house.The doors and windows are now in place so the site can be locked up at night. 

This is a photo of the ground floor entrance.  The dark grey rubber material is water proofing for the walls. It is covered in a wire mesh which is going to hold the mortar render finish.

september26k

The master bedroom walk in closet.  You can see the insulation pads on the external walls.

september26b

The bath room to be.

september26c

This is the second floor looking back to the dining and kitchen. This is a nice big room.  You can see the light in the foreground from the sky-lights.

september26g

The internal balcony on the second floor.  We are quite happy with this space.  It is giving the second floor an open feeling without losing privacy.

september26h

The third floor deck. This deck has BBQ written all over it.

september26f

The project has certainly taken longer than forecast, we were expecting to be marketing the finished house by now.  We realise now  it  takes much more thime to build something nice using an architect than to build  a standard kit home.  The builder tells us now he should be done by the end of October although he still has a lot to do !

Share and Enjoy:
  • Digg
  • del.icio.us
  • Facebook
  • Google Bookmarks
  • LinkedIn
  • MySpace
  • Reddit
  • StumbleUpon
  • Technorati
  • Twitter
  • E-mail this story to a friend!
  • Print this article!
Subscribe to Feed

Related Articles:

Leave your comment here