The builders were finally able to start in the first week of June.  We purchased the land in February so it has taken about four months for the design, planning, approval and price negotiations.

They start by excavating the site to so they can build the foundations. 

breezejune9

Crushed rock is then added to make a nice hard and stable base.

june25c

june25b

june25a

Work then begins on the foundations.

breezejuly2a

Progress is a bit slow because we are in the middle of the rainy season.  The builders are unable to work on the foundations when it is raining.

By July 13th the foundations are starting to take shape.

july13a

july13d

We should be finished with the foundations in the next week or so.  Now the rainy season is over we should see things move along a little more quickly.

This entry was posted in Building Your Own House. Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>